Cajalco Road from Temescal Canyon Road to I-215
PROJECT WEBSITE: Cajalco Road Widening
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory

California
Description:
The Riverside County Transportation Department is proposing to widen and realign Cajalco Road between Temescal Canyon Road to the west and Interstate 215 (I-215) to the east. The project is located in Riverside County, California and covers a distance of approximately 16 miles. A small portion of the westernmost part of the alignment is located in the city of Corona. The project would widen the roadway to four lanes between Harvill Avenue and Temescal Canyon Road, and to six lanes between the I-215 southbound ramps and Harvill Avenue.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|