Southeast Gateway Line Project (formerly West Santa Ana Branch Transit Corridor)
PROJECT WEBSITE: Southeast Gateway Line
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of Defense, US Army Corps of Engineers - Regulatory
Description:
The Los Angeles County Metropolitan Transportation Authority (LACMTA) proposes to construct a light rail transit (LRT) system that would connect several cities and communities in southeast Los Angeles County, California. The Project's initial segment, and Locally Preferred Alternative (LPA) consists of a 14.5 mile LRT segment that would connect several cities between its termini at the Slauson/A Line (blue) connection and Pioneer stations, and would include shifting/realignment of existing freight rail for a distance of approximately 8.7 miles along this alignment. The project includes nine stations plus a tenth station on the "C" Line at I-105, five with parking facilities, and one Maintenance and Storage Facility.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|