USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Planned
The project sponsor’s delayed submission of information needed for a complete Marine Mammal Protection Act (MMPA) Incidental Take Authorization (ITA) application has resulted in delays to the schedule for NMFS’s issuance of the proposed ITA as well as delays to the development of complete Endangered Species Act (ESA) and Essential Fish Habitat (EFH) consultation documents, the Draft Environmental Impact Statement (DEIS), the Final Environmental Impact Statement (FEIS) and all other subsequent dependent milestones. BOEM developed an updated permitting timetable reflecting the 90-day shift to the DEIS, FEIS, and Record of Decision (ROD) milestone dates. The NEPA Action is impacted by the milestone shifts for the ESA Action as a result of the shifts for the MMPA Action; the NEPA timeline is changing accordingly. Finally, the completion dates for EPA’s OCS air permit  are all dependent on the final completion date for the NEPA action.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 11-01-2022 11-01-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 03-29-2024 05-01-2024 --- No
OCS Air Permit application complete (Applicant Action) 09-30-2024 12-30-2024 --- No
Issuance of final decision/permit approval (Agency Action) 09-30-2025 12-30-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 11-01-2022 11-01-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 03-29-2024 03-29-2024 --- No
OCS Air Permit application complete (Applicant Action) 09-30-2024 09-30-2024 --- No
Issuance of final decision/permit approval (Agency Action) 09-30-2025 09-30-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 11-01-2022 11-01-2022 --- No
OCS Air Permit application submitted (Applicant Action) 03-29-2024 03-29-2024 --- No
OCS Air Permit application complete (Applicant Action) 09-30-2024 09-30-2024 --- No
Issuance of final decision/permit approval (Agency Action) 09-30-2025 09-30-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 11-01-2022 11-01-2022 --- No
OCS Air Permit application submitted (Applicant Action) 03-29-2024 03-29-2024 --- No
OCS Air Permit application complete (Applicant Action) 09-30-2024 09-30-2024 --- No
Issuance of final decision/permit approval (Agency Action) 09-30-2025 09-30-2025 --- No