USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
Coastal Virginia Offshore Wind Commercial Project, Outer Continental Shelf (OCS) Air Permit No. OCS-R3-01 was issued on April 9, 2024, ahead of the scheduled target date of April 30th, 2024. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-01-2021 12-01-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 09-03-2021 03-15-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 09-15-2022 02-07-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 09-15-2023 04-09-2024 --- Yes
In Progress
EPA requested additional clarifying information on June 29, 2023 and the project sponsor submitted a revised application on July 31, 2023.  EPA identified that the project sponsor used outdated emissions factors as inputs to their modeling on August 17, 2023.  The project sponsor provided proposed revised emissions factors on September 8, 2023.  Follow-up questions led to meetings with the project sponsor on September 28, 2023 and October 12, 2023.  The project sponsor submitted a revised application and modeling data on November 15, 2023.  EPA needs to perform a modeling review based on this new modeling.  Because of the new modeling analyses and revised emission estimates, EPA is requesting to adjust the February 7, 2024, milestone date for issuance of the final permit decision.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-01-2021 12-01-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 09-03-2021 03-15-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 09-15-2022 02-07-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 09-15-2023 04-30-2024 --- No
In Progress
The target date for the final OCS Air Permit milestone is 1-year after the date EPA determines the permit application is complete.  Since the OCS Air Permit application was deemed complete on 2/7/23, the date for the OCS Air Permit issuance of final decision is being adjusted accordingly.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-01-2021 12-01-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 09-03-2021 03-15-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 09-15-2022 02-07-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 09-15-2023 02-07-2024 --- No
In Progress
EPA deemed the application complete ahead of the 2/11/23 posted target date.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-01-2021 12-01-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 09-03-2021 03-15-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 09-15-2022 02-07-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 09-15-2023 09-15-2023 --- No
Planned
Sponsor delays in complete application submission.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-01-2021 12-01-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 09-03-2021 03-15-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 09-15-2022 02-11-2023 --- No
Issuance of final decision/permit approval (Agency Action) 09-15-2023 09-15-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) --- 12-01-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) --- 03-15-2022 --- Yes
OCS Air Permit application complete (Applicant Action) --- 09-15-2022 --- No
Issuance of final decision/permit approval (Agency Action) --- 09-15-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) --- 12-01-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) --- 03-15-2022 --- No
OCS Air Permit application complete (Applicant Action) --- 09-15-2022 --- No
Issuance of final decision/permit approval (Agency Action) --- 09-15-2023 --- No