Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-22-2021 12-22-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 12-27-2021 09-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 12-27-2021 08-21-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 12-27-2021 09-30-2024 --- Yes
In Progress
The basis for EPA's request to extend the final completion date for the OCS air permit is that this action is dependent upon the timing of BOEM’s issuance of a FEIS and ROD to conclude its NEPA review. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-22-2021 12-22-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 12-27-2021 09-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 12-27-2021 08-21-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 12-27-2021 09-30-2024 --- No
In Progress
EPA (Region 2) deemed the Project Sponsor’s OCS air permit application complete on August 21, 2023.  Accordingly, the requested final completion date for the OCS air permit action is August 21, 2024. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-22-2021 12-22-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 12-27-2021 09-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 12-27-2021 08-21-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 12-27-2021 08-21-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-22-2021 12-22-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 12-27-2021 09-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 12-27-2021 08-21-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 12-27-2021 12-29-2023 --- No
Planned
To issue permit EPA needs the published ROD. This date has been moved to accommodate the ROD Date move due to the delay of the DEIS. 3/31 shifting to 6/30 - Sponsor delays in complete application submission. 6/15 - EPA unable to deem application complete by 6/30 and would like to move this to 9/30 to give ample time to review applicant's latest submittal and modeling analysis. 8/8 - Application submitted June 30 and additional supplemental materials submitted on 7/20.  30 day review will be 8/20 (due to holiday this is being put as 8/21)  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-22-2021 12-22-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 12-27-2021 09-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 12-27-2021 08-21-2023 --- No
Issuance of final decision/permit approval (Agency Action) 12-27-2021 12-29-2023 --- No
Planned
EPA Region 2 is requesting to change the scheduled date of complete application received from 12/1/2022 to 3/31/2023 since we have requested the applicant to submit before 11/1/2022 significant additional information for the air permit application to be complete. Also, we coordinate our OCS completeness determination with the USFWS for the Class I area air impacts. The air permit application cannot be deemed complete until both EPA and the USFWS received all of the required information. The 12/1/2022 milestone must be changed to 3/31/2023.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-22-2021 12-22-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 12-27-2021 09-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 12-27-2021 03-31-2023 --- No
Issuance of final decision/permit approval (Agency Action) 12-27-2021 12-29-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-22-2021 12-22-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 12-27-2021 09-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 12-27-2021 12-01-2022 --- No
Issuance of final decision/permit approval (Agency Action) 12-27-2021 12-29-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-22-2021 12-22-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 09-01-2022 09-01-2022 --- No
OCS Air Permit application complete (Applicant Action) 12-01-2022 12-01-2022 --- No
Issuance of final decision/permit approval (Agency Action) 12-29-2023 12-29-2023 --- No