USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
The NPDES permit was issued on 6/13/2024, ahead of the target date of 06/21/2024, and can be found at this link: https://www3.epa.gov/region1/npdes/permits/2024/finalma0004940permit-2024.pdf
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 12-01-2021 12-01-2021 --- Yes
Completed application received (Applicant Action) 01-03-2022 01-03-2022 --- Yes
EPA authorizes discharge under Individual permit (Agency Action) 09-29-2023 06-13-2024 --- Yes
In Progress
The project sponsor provided BOEM notice on June 26, 2023 of plans to initiate onshore construction activities. The notice provided information on their planned work at the Onshore Converter Station and laydown yards (Phase 1A activities, scheduled to start around July 10), and installation of splice vaults and duct banks, and the expansion of an existing substation (Phase 1B activities, scheduled to commence around September). BOEM notified Tribal Nations, cooperating agencies, Section 106 consulting parties, and the project sponsor that BOEM did not have authority over these activities and that onshore construction would be moving forward.  While BOEM does not have authority over these onshore activities, BOEM has a responsibility to analyze impacts from all the proposed onshore activities included within the scope of a project as connected actions under the National Environmental Policy Act (NEPA) and Section 106 of the National Historic Preservation Act (NHPA). A Construction and Operations Plan (COP) update was required to move forward with these analyses because the prior COP dated August 18, 2022, did not include enough detailed information regarding the onshore activities. The project sponsor submitted an updated COP to BOEM on September 29, 2023. The updated information was necessary for determining the timeline for concluding the Section 106 process and Record of Decision.  Movement of the ROD is therefore causing movement of this dependent action.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 12-01-2021 12-01-2021 --- Yes
Completed application received (Applicant Action) 01-03-2022 01-03-2022 --- Yes
EPA authorizes discharge under Individual permit (Agency Action) 09-29-2023 06-21-2024 --- No
In Progress
In addition to interagency delays in developing project alternatives in June 2022, the project sponsor presented new project information in February 2023, to BOEM, NOAA, and USACE. The change in design for feasible wind turbine generator (WTG) locations involved removing 22 WTGs for the project due to glauconite sands present within the Lease Area. This change required additional analysis by BOEM for a new constructible preferred alternative that needed to be added to FEIS. The project design changed the impacts analysis for consultations.  This action is dependent upon completion of the ROD.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 12-01-2021 12-01-2021 --- Yes
Completed application received (Applicant Action) 01-03-2022 01-03-2022 --- Yes
EPA authorizes discharge under Individual permit (Agency Action) 09-29-2023 03-04-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 12-01-2021 12-01-2021 --- Yes
Completed application received (Applicant Action) 01-03-2022 01-03-2022 --- Yes
EPA authorizes discharge under Individual permit (Agency Action) 09-29-2023 09-29-2023 --- No