Alaska Cargo and Cold Storage EA
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/01/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY
Project Category
DOT Projects
![Department of Transportation Department of Transportation](/sites/permits.dot.gov/files/styles/project_page_icon/public/2021-03/agency-department-of-transportation-icon-91x91.png?itok=fl6ufL7h)
LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Description:
ACCS proposes to construct cold storage facilities at Ted Stevens Anchorage International Airport including aircraft parking apron, warehouse, hardstand fuel distrubition, equipment shop and road connection to Postmark Drive.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|