FAST-41 Initiation Notice provided by the lead agency.
Application has not been received by the USACE.
No decision has been made due to no application received
N/A
None at this time.
Not available at this time.
FAST-41 Initiation Notice provided by the lead agency.
Application has not been received by the USACE.
No decision has been made due to no application received
N/A
None at this time.
Not available at this time.
FAST-41 initiation July 6, 2017
Original application received by BLM December 19, 2007. Contact BLM Project Manager for additional information.
In keeping with its mission and NEPA, BLM has established collaborative relationships with many Federal, State and local organizations to facilitate cooperative government reviews, ensure science-based decision-making, and prevent duplicative efforts. As part of this approach, BLM incorporates input from the public and affected local governments into the review process. BLM relies on this input to develop an Environmental Impact Statement (as required by 30 CFR 550.269) to support its decision-making process.
BLM NEPA - Boardman to Hemingway Project
The FIN will be posted by the Lead Agency.
Application and supporting documents are dependent on submittal of a final Plan of Development (POD). A final, complete POD has not yet been received.
Mitigation measures were partially identified in the 2018 Record of Decision. Final and complete mitigation measures will be dependent on submittal of a final Plan of Development (POD) and application.
None.
All public engagement is complete as of the 2018 ROD.
Agency action (or decision) is dependent on submittal of a final Plan of Development (POD) and application.