Completion of the Route 7 and Route 15 Interchange
PROJECT WEBSITE: Route 7/15 Norwalk Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/30/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
The purpose of the project is to improve roadway system linkage between Route 7 and the Merritt Parkway at Interchange No. 39; improve the mobility for vehicles at Interchanges No. 39 & No. 40; and improve the mobility for all modal users along the immediate adjacent local roadway network (Main Avenue, Glover Avenue, and Creeping Hemlock Drive); and improve safety throughout the project area. The project looks to reduce congestion, provide long term context-sensitive serviceability, and optimize value gained from Public investment in the project.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|