1118000084 - SD-76 Culvert Rehab (Priority #15)

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/18/2023

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Description:

The SR-76 corridor has approximately l 00 pipe culvert systems that have been identified with
deficiencies such as poor pipe, poor pipe invert, poor joint, poor inlet or outlet condition, and
poor waterway condition. Each system includes one or multiple culvert segments. The proposed
culvert rehabilitation strategies include replacement, sealing joint repair, alternative pipe liners
and possibly upsizing the pipe size where appropriate.
Additional end treatment repairs are needed along SR-76 which include, repairing flared end
sections and pipe end sections or headwalls, joint sealing/repair, stabilizing embankments, either
debris removal or sediment flushing, removing vegetation, regrading channels, and adding end
treatments.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete