ANC Runway 15/33 Rehabilitation, Environmental Assessment

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/16/2017

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation

SECTOR
Aviation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Description:

The proposed work would include the following:

  • Rehabilitate RW 15/33
  • Shift RW 33 displaced threshold north to separate the RW 15/33 RSA from the RW 7L/25R RSA
  • Shift RW 15 threshold north and remove displaced threshold to maintain minimum LDA as a result of the RW 33 threshold change
  • Revise the declared distances for RW 15/33
  • Revise taxiway geometry to accommodate the widened runway
  • Replace runway and taxiway lighting
  • Remove the RW 15 ODALS and replace with a MALSF
  • Reconstruct Taxiway Q to provide access to the relocated RW 15 threshold

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete