Arroyo De La Laguna: Replace/Rehab Bridge for Scour Mitigation, Bridge Rail Upgrade and Seismic Retrofit

PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-4/d4-projects/d4-alameda-84-arroyo…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/30/2025

4 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

California

California

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

The California Department of Transportation (Caltrans) proposes to mitigate bridge scour for the Arroyo de la Laguna Bridge Project on State Route 84 in the Niles Canyon Corridor (SR-84) at postmile 17.2 in the town of Sunol. In addition, Caltrans proposes to protect the bridge's structural integrity and improve safety by directing potentially errant vehicles back into the roadway. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete