Atlanta - Chattanooga High Speed Ground Transportation

PROJECT WEBSITE: GDOT Atlanta to Chattanooga HSGT

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/12/2017

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Railroad Administration

Description:

The Georgia Department of Transportation (GDOT) is preparing a Tier I Environmental Impact Statement (EIS) to evaluate the general environmental and related impacts of constructing and operating a high-speed ground transportation (HSGT) system between Atlanta, Georgia and Chattanooga, Tennessee for the Federal Railroad Administration (FRA) and Federal Highway Administration (FHWA) of the US Department of Transportation and in cooperation with the Tennessee Department of Transportation. The goals of the Tier I EIS process are to: 1) examine the regional transportation implications of the project concept; 2) evaluate the modal and technology alternatives available to provide HSGT between the two cities; 3) develop and evaluate location alternatives; and 4) determine the logical segments to be carried forward for detailed evaluation in subsequent (Tier II) environmental documents.

Notice of Intent. 

The Atlanta to Chattanooga High Speed Rail Ground Transportation project (Project) is a proposed high speed intercity passenger rail project running the approximately 120 miles between Atlanta, Georgia and Chattanooga, Tennessee.  Although not one of FRA’s designated high speed rail corridors, GDOT studied this corridor as part of Georgia’s 1997 Intercity Rail Plan, which recommended further study of the corridor with an emphasis on high-speed service.  Subsequently, Congress appropriated $7 million ($5 million from TEA-21 and $2 million from the FY 2004 Consolidated Appropriations) to FHWA to further study the corridor. FHWA transferred those funds to FRA.  The Project would provide a competitive and more reliable transportation choice for people traveling between Atlanta and Chattanooga and represents a response to numerous transportation-related needs in the corridor. 
 
FRA is serving as the lead federal agency for the environmental review with GDOT and TDOT as our state partners preparing this draft environmental impact statement (DEIS).  Initially, FHWA was a Co-Lead Agency, but they have reduced their role to that of Participating Agency.  The EIS is a program-level Tier I document looking at general impacts and will support FRA, GDOT and TDOT in making decisions concerning equipment (including train technology), maximum operating speeds, and which alignments and station location options to select for more detailed technical analysis during subsequent preparation of a Tier II project-level environmental document. 

On September 12, 2017, the FRA signed a combined FEIS ROD. 

For more information on the Project, including dates and locations for the public meetings and instructions on how to submit comments, please visit GDOT’s Project webpageExternal Link.

Draft Environmental Impact Statement

Atlanta - Chattanooga Tier I Draft Environmental Impact Statement (DEIS)
DEIS Appendices A–D
DEIS Appendix E, Chapters 1–8
DEIS Appendix E, Chapter 9
DEIS Appendix E, Chapters 10–12; Appendix F 


In addition, pertinent information can be found at the project's FRA webpage, https://www.fra.dot.gov/Page/P0451.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete