Ballard Link Extension Project

PROJECT WEBSITE: https://www.soundtransit.org/system-expansion/ballard-link-extension

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/15/2028

0 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

The Ballard Link Extension Project proposed by Sound Transit would expand Link light rail service along a 7.7-mile corridor through downtown Seattle, from SODO to Ballard, and include a new 3.3-mile light rail-only tunnel from south of the Chinatown-International District to South Lake Union and Seattle Center/Uptown. Stations would serve the following areas: Chinatown International District, Midtown, Westlake, Denny, South Lake Union, Seattle Center, Smith Cove, Interbay and Ballard. The purpose of the project is to extend existing light rail service through Downtown Seattle, to make appropriate community investments to improve mobility, and to increase capacity and connectivity for regional connections. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete