Bicentennial Blvd

PROJECT WEBSITE: TxDOT Get Involved

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/19/2018

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The proposed project would extend Bicentennial Boulevard from Trenton Road to SH 107 as a new location, four-lane facility. The proposed 2.86-mile roadway extension would consist of a 12-foot wide inside travel lane (one in each direction), a 14-foot wide outside shared use lane for vehicles and bicycles (one in each direction), and five-foot wide sidewalks for pedestrians. Other improvements include 13-foot wide left turn lanes at cross streets, curb and gutter, and drainage improvements. The proposed Bicentennial Boulevard Extension Project would require approximately 1.9 acres of additional ROW, and approximately 0.6 acre of temporary construction easements and 0.2 acre of permanent easements needed for anticipated construction of proposed noise barriers.

The proposed Bicentennial Boulevard improvements include:

  • Constructing a new bridge
  • Constructing new sidewalks

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete