Bloomfield Municipal Airport Land Acquisition, Pond Removal, and Construction of a Parallel Taxiway, Environmental Assessment
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Description:
Update: This project was changed from EA to CATEX after coordinating with resource agencies and finding no resources would be impacted.
An Environmental Assessment (EA) is being prepared for proposed development at the Bloomfield Municipal Airport subject to the National Environmental Policy Act (NEPA). The Federal Aviation Administration (FAA) is the lead federal agency for the NEPA document.
The proposed project at the airport includes the following:
• Land Acquisition (25 acres in fee, 14 acres in easement) for Runway 18/36 approach and departure protection
• Drain and fill ponds on existing airport property to eliminate hazardous wildlife attractants
• Construct approximately 12,500 linear feet of fencing to delineate and prevent intrusion onto airport property
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|