USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Bloomfield Municipal Airport Land Acquisition, Pond Removal, and Construction of a Parallel Taxiway, Environmental Assessment

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Cancelled

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation

SECTOR
Aviation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Description:

Update: This project was changed from EA to CATEX after coordinating with resource agencies and finding no resources would be impacted.

An Environmental Assessment (EA) is being prepared for proposed development at the Bloomfield Municipal Airport subject to the National Environmental Policy Act (NEPA). The Federal Aviation Administration (FAA) is the lead federal agency for the NEPA document.  

The proposed project at the airport includes the following:
• Land Acquisition (25 acres in fee, 14 acres in easement) for Runway 18/36 approach and departure protection
• Drain and fill ponds on existing airport property to eliminate hazardous wildlife attractants 
• Construct approximately 12,500 linear feet of fencing to delineate and prevent intrusion onto airport property

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete