Bob Hope “Hollywood Burbank” Replacement Terminal Environmental Impact Statement
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/21/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Description:
The Burbank-Glendale-Pasadena Airport Authority, owner of Bob Hope Hollywood Burbank Airport (BUR), is proposing to construct a replacement airline passenger terminal, aircraft parking apron, and related actions. This project will enhance airport safety. BUR’s existing terminal is located within the airport’s designated object free areas (OFA) and penetrates the airport’s primary surface (as outlined in 14 Code of Federal Regulations Part 77, Safe, Efficient Use, and Preservation of the Navigable Airspace). The replacement terminal will address these issues.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|