USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Broward Commuter Rail South Project

PROJECT WEBSITE: https://www.fdot.gov/projects/broward-commuter-rail-south/home

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/05/2024

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

Broward County proposes to implement commuter rail service along 11.5 miles of the existing Florida East Coast (FEC) Railway from the Brightline Aventura Station in Miami-Dade County to the Broward Health Medical Center in Fort Lauderdale. The proposed project includes three stations and parking facilities that are expected to be built within existing city, county, and/or FEC Railway properties along with corresponding improvements to the existing Hialeah Maintenance Facility in Miami-Dade County. Other elements include track, signaling, and safety and communication improvements along the corridor, as well as acquisition of rolling stock for the service. According to Broward County, the project plans to share the FEC Railway with freight trains and intercity passenger trains.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete