Bruckner Expwy - Hutchinson Pkwy Mobility Improvement Project, Bronx Co., NYC

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/05/2021

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

The Build Alternative reconfigures the I-95/Pelham Parkway Interchange, extends the I-95 northbound fourth travel lane to exit to the Hutchinson River Parkway, constructs a new exit ramp from northbound Hutchinson River Parkway to Bartow Avenue, and reconfigures and improves the operation and safety of the pedestrian/bicyclist paths within the I-95/Pelham Parkway Interchange, Pelham Bay Park in the vicinity of the interchange, and along Bartow Avenue near the Hutchinson River Parkway. This alternative will improve traffic flow, vehicular and pedestrian/bicyclist safety along the northbound I-95 ramps, improve geometric and operational deficiencies associated with the I-95 ramps, and provide direct access to Co-op City, thereby satisfying the Project purpose and objectives.  

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete