Canarsie Tunnel Project Supplemental Environmental Assessment and Section 4(f) Review
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/14/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Description:
The Metropolitan Transportation Authority New York City Transit (MTA NYCT) is proposing a change to the approved Canarsie Tunnel Project. The Project includes rehabilitation, resiliency, state of good repair and capacity improvement activities related to the Canarsie Tunnel, which is located in New York under the East River and connects Manhattan and Brooklyn. The purpose of the proposed change is to provide transportation alternatives, known as the Alternative Service Plan (ASP), to the greatest number of diverted L train riders while the Canarsie Tunnel is undergoing rehabilitation. The Tunnel was damaged during Hurricane Sandy in 2012 and needs to be repaired in a safe and expeditious manner to minimize risk of unexpected structural failure and service disruptions. At the time of FTA’s previous environmental review, the Project included a preliminary concept of a service plan to provide transportation alternatives. The ASP has been refined and FTA and MTA NYCT have prepared a Supplemental Environmental Assessment to present the potential environmental impacts of the proposed ASP.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|