Canyon Road East Northerly Extension Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Washington
Description:
The River Crossing Project is one of two elements of the Canyon Road Regional Connection project. This element proposes to extend Canyon Road East from 52nd Street East in Puyallup to 70th Avenue East in the City of Fife. The project as proposed would support regional companies in their effort to retain and expand family-wage jobs, extend Canyon Road East from south of Pioneer Way East to 52nd Street East and from 52nd Street to 70th Avenue East, build a bridge over the Burlington Northern and Santa Fe railroad to separate vehicles on the road from train traffic, build a new, more efficient bridge over the Puyallup River, including improved bicycle and pedestrian connections, and remove the existing Milroy Bridge, constructs stormwater treatment and storage facilities, install new traffic signals, curbs, gutters and sidewalks, and create a wetland
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|