Cape May County Airport Development Project Environmental Assessment
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/13/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Description:
The proposed project includes construction of an approximately 5,600 square foot (SF) Multi-Purpose Building and an approximately 20-space parking lot within a previously developed area of the Airport.
• Demolition of two 3,000 +/- SF hangars (Hangar 12 & Hangar 14)
• Demolition of the 1,000 +/- SF DRBA operations shack.
• Pavement demolition (1,000 SY parking/driveways & 3,000 SY apron/sidewalks/slabs).
• Site work – includes grading, drainage, asphalt paving (1,700 SY), sidewalks (500 SY), LED parking lot lighting (4 light poles), installation of security fence/gates (320 LF), and landscaping.
• Extension/installation of water/sewer lines, electrical/communication conduits, and structures.
• Converting approximately 2,300 SY of existing PCC Apron “B” from airside to landside and relocation of the perimeter fence to make room for a portion of the proposed Multi-Purpose Building and parking area.
• Stormwater management
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|