Capital Boulevard North Upgrade (Raleigh to Wake Forest)
PROJECT WEBSITE: https://www.ncdot.gov/projects/capital-boulevard-upgrade/Pages/default.aspx
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/30/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of Defense, US Army Corps of Engineers - Regulatory
Description:
Upgrade approximately 10.5 miles of US 1 (Capital Boulevard) from I-540 in Raleigh to SR 1909 (Purnell Road)/SR 1931(Harris Road) in Wake Forest in Wake County. Proposed improvements include upgrading US 1 from a median-divided roadway with partial access control to a fully controlled-access freeway as well as improving existing and constructing new interchanges and service roads.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|