Chesapeake Bay Crossing Study Tier 2 EIS

PROJECT WEBSITE: https://baycrossingstudy.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/16/2026

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

Also known as the Chesapeake Bay Crossing Study Tier 2, the purpose of the Tier 2 is to address existing and future transportation capacity needs and access across the Chesapeake Bay and at the Chesapeake Bay Bridge approaches along the U.S. 50/301 corridor. The Tier 2 is evaluating measures to reduce congestion; improve travel times and reliability, mobility, and roadway deficiencies; and accommodate maintenance activities and navigation while minimizing impacts to local communities and the environment. Logical Termini of the project is from the MD 2/MD 450 interchange in Anne Arundel County to the U.S. 50 and U.S. 301 split in Queen Anne’s County which is approximately 21 miles in length.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete