Congestion Pricing- VPPP

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/23/2023

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Other Agencies with Actions or Authorizations:

No icon

New York

Description:

The Triborough Bridge and Tunnel Authority (TBTA)—an affiliate of the Metropolitan Transportation
Authority (MTA)—the New York State Department of Transportation (NYSDOT), and the New York City
Department of Transportation (NYCDOT) are the Project Sponsors for the Manhattan Central Business
District (CBD) Tolling Program (the CBD Tolling Program or the Project), in New York, New York. In
cooperation with the Federal Highway Administration (FHWA) as the lead Federal agency, the Project
Sponsors are preparing an Environmental Assessment (EA) in accordance with the National Environmental
Policy Act (NEPA).1 The EA will analyze the potential environmental effects of implementing the CBD Tolling
Program.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete