USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Dallas to Houston High Speed Rail

PROJECT WEBSITE: Dallas to Houston High-Speed Rail – Passenger Service from Houston to Dallas

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/10/2020

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Railroad Administration

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Federal Railroad Administration (FRA) prepared an Environmental Impact Statement (EIS) in compliance with the National Environmental Policy Act (NEPA) to assess the potential beneficial and adverse environmental impacts of FRA’s proposed rulemaking to enable effective safety oversight of the operation of a high-speed rail (HSR) system based on the Japanese N700-Series Tokaido Shinkansen technology that is described in a Petition for Rulemaking for a Rule of Particular Applicability (RPA) submitted by Texas Central Railroad, LLC (TCRR). TCRR’s petition for rulemaking contains TCRR’s proposal to construct and operate an approximately 240-mile, for-profit, HSR system connecting Dallas and Houston based on the Japanese N700-Series Tokaido Shinkansen technology (the Project).

On March 10, 2020, FRA published a Notice of Proposed Rulemaking (NPRM), proposing a set of minimum Federal safety standards to enable effective safety oversight of the operation of TCRR’s HSR system within the United States. NEPA requires issuance of a Record of Decision (ROD) in order to complete the EIS process, which must be done prior to or concurrent with issuance of a final rule.

As part of the NEPA process, FRA completed an independent evaluation of potential HSR corridor alternatives and determined that the Utility Corridor is the only feasible end-to-end corridor alternative. FRA’s Alternatives Analysis Technical Report documents the potential HSR corridor alternatives that were evaluated, and describes FRA’s screening process.

Following a comprehensive analysis of major corridors proposed for the project, FRA identified six draft alignment alternatives for further evaluation in the Draft EIS

Through the natural progression of the NEPA process, FRA narrowed the focus of its environmental analysis in its Alignments Alternatives Analysis Report. FRA evaluated 22 potential route alternatives within five major geographical areas using environmental constraints screening criteria, as required by NEPA. As part of the EIS, the environmental and social impacts of various alternative HSR route alignments were analyzed including possible routes that share corridors with an existing rail line and along electric utility lines. TCRR’s proposed HSR line would operate on a dedicated right-of-way and would not share track or infrastructure with existing trains or rail lines. In addition, the EIS analyzed the potential impacts of stations, power or fueling stations, and maintenance facilities to support HSR operations.      

FRA released the Final EIS on May 29, 2020, and accepted public comments on the Draft Section 106 Programmatic Agreement (Appendix L of Final EIS) through July 28, 2020.

On September 10, 2020 , FRA issued a final rule that establishes safety standards for the TCRR HSR system. The final rule is not intended for general application in the railroad industry, but applies only to the TCRR system. The TCRR HSR system will operate from Houston to Dallas, on dedicated track, with no grade crossings, at speeds not to exceed 330 km/h (205 mph). The TCRR rolling stock, track, and core systems will replicate the Tokaido Shinkansen HSR system operated by the Central Japan Railway Company, and will be used exclusively for revenue passenger service.

FRA’s ROD for the Dallas to Houston HSR Environmental Impact Statement is contained in the final rule.

The ROD attachments can be accessed via the links below.

Currently, this project is 100% privately funded.


In addition, pertinent information can be found at the project's FRA webpage, https://railroads.dot.gov/dallas-houston-high-speed-rail/dallas-houston-high-speed-rail-passenger-service-houston-dallas

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete