Earthquake Ready Burnside Bridge
PROJECT WEBSITE: Earthquake Ready Burnside Bridge
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/20/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Oregon
Department of the Army, US Army Corps of Engineers - Civil Works
Department of Homeland Security, US Coast Guard
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The primary purpose of this project is to create a seismically resilient Burnside Street lifeline crossing of the Willamette River that will remain fully operational and accessible for vehicles and other modes of transportation immediately following a major CSZ earthquake. A seismically resilient Burnside Bridge will support the region’s ability to provide rapid and reliable emergency response, rescue and evacuation after a major earthquake, as well as enable post-earthquake economic recovery. In addition to ensuring that the crossing is seismically resilient, the purpose is also to provide a long-term, low-maintenance and safe crossing for all users.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|