East San Fernando Valley Transit Corridor

PROJECT WEBSITE: East San Fernando Valley Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/29/2021

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

The Los Angeles County Metropolitan Transportation Authority proposes an approximately 6.7-mile transit corridor project to improve north-south mobility in the eastern San Fernando Valley in Southern California, offering additional transit options and increasing access to transit near the corridor.  The proposed Project would extend along Van Nuys Boulevard from the Metro Orange Line (located just north of Oxnard Street) in the south in the City of Los Angeles to San Fernando Road where it proceeds to the City of San Fernando and the Sylmar/San Fernando Metrolink Station in the north. The following alternatives are under consideration: No Build; Transportation Systems Management; Build Alternative 1- Curb Running Bus Rapid Transit (BRT); Build Alternative 2- Median Running BRT; Build Alternative 3- Median Running Tram; Build Alternative 4-Light Rail Transit. For Alternatives 3 and 4, a new maintenance facility would be needed to store and maintain the light rail/tram cars. Three candidate locations have been identified for the facility.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete