East-West Corridor
PROJECT WEBSITE: https://cityofyakima-terraceheights.org
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Washington
Description:
This project proposes to create a new transportation corridor between the City of Yakima and the community of Terrace Heights. As the population of Terrace Heights has grown rapidly in recent years and the population is projected to continue increasing, an additional corridor is necessary to provide an alternative crossing of the Yakima River. The Yakima River is a significant barrier to transportation between these two areas and currently the only direct crossing from downtown Yakima is the Yakima Avenue/Terrace Heights Drive route, approximately 0.6 miles south of the project area.
The logical termini for this project are the 1st Street and H Street intersection in the City of Yakima and east of the Roza Canal Wasteway #2 in the Terrace Heights neighborhood, where it will connect to Yakima County's easternmost phase of the corridor. The project will include a 3 to 4- lane roadway, an underpass to cross Interstate 82 (1-82), a bridge over the Yakima River, a bridge over the Roza Canal Wasteway #2, a shared-use path, sidewalks, curbing, gutters, and illumination.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|