Eastside Transit Corridor Phase II
PROJECT WEBSITE: Eastside Transit Corridor Phase 2
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Description:
The Los Angeles County Metropolitan Transporation Authority (LAMCTA) proposes to extend the existing Metro Gold Line Eastside Extension from the Atlantic Station terminus in an easternly direction by 6.9 to 9.5 miles. The light rail extension currently has two build alternatives that include the SR 60 North Side Design Variation which terminates in the City of South El Monte and the Washington Boulevard alternative which terminates in the City of Whittier. The Draft Environmental Impact Statement was completed on 8/12/14 with a 60-day public comment period that ended on 10/21/14. Based upon the public comments received from stakeholders and project cities, there was strong support for both alternatives. Comments received from Cooperating and Public Agencies expressed a need to conduct additional technical studies in order to provide the additional detail necessary to address comments in their area of expertise and jurisdiction. These technical studies are currently under way. Once the technical studies are completed, a timeline for the Final Environmental Impact Statement will be determined.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|