Erbie Road Improvement Project (EA)
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/16/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
The National Park Service (NPS), in cooperation with the Federal Highway Administration (FHWA), proposes to rehabilitate a 2.58-mile damaged section of Compton-Erbie Road (County Road 19) and to replace two low-water crossings in the Erbie area. All of the proposed work lies within the Buffalo National River (park), in Newton County, Arkansas. In May of 2015, a major storm event caused widespread damage in the park. Along with repair of the storm damage, improvements are necessary to reduce the likelihood of damage from future storm events.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|