Federal Way City Center Access Project
PROJECT WEBSITE: https://www.cityoffederalway.com/page/city-center-access-project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/17/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of Commerce, National Oceanic and Atmospheric Administration
States
Department of the Interior, Fish and Wildlife Service
Description:
The Project is located in Federal Way (King County, Washington) on both sides of I-5 in the vicinity of milepost 144 along S 320th Street, S 324th Street, and 23rd Avenue S. The Project proposes to make several improvements for mobility and access, including the following elements:
• Modification of the S 320th Street interchange by adding braided ramps and access at S 324th Street.
• Construction of a new two-lane bridge over I-5 at S 324th Street.
• Extension of S 324th Street from 23rd Avenue S to Weyerhaeuser Way S.
• Widening S 324th Street from State Route 99 to 23rd Avenue S.
• Improvements to S 320th Street, including replacing the existing bridge and widening S 320th Street east of I-5 to add high-occupancy vehicle lanes.
• Nonmotorized improvements along 23rd Avenue S, S 320th Street, and S 324th Street.
• Stream crossing upgrades to improve fish passage, including under I-5.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|