Five Cities Multimodal Transportation Network Enhancement Project
PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-5/district-5-current-projects/05-1…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/26/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:
California
Department of the Interior, Fish and Wildlife Service
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The California Department of Transportation(Caltrans) and the San Luis Obispo Council of Governments (Council of Governments) are proposing an operational improvement project to address traffic delays that occur during periods of high traffic volumes on the southbound lanes of US101 through Shell Beach and Pismo Beach. The proposed project would widen the inside shoulder of the highway from the vicinity of San Luis Obispo Creek to the railroad overhead in Pismo Beach to serve as a travel lane strictly during periods of heavy traffic volumes.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|