USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Five Points Transformation Project

PROJECT WEBSITE: https://www.fivepointstransformation.com/home

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/25/2024

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

The Metropolitan Atlanta Rapid Transit Authority (MARTA) proposes to modernize the Five Points rail station in downtown Atlanta, Georgia. The Five Points Transformation project will demolish the existing station canopy, construct a new canopy, and redesign the plaza area entirely within the same geographic footprint of the existing plaza. The Project proposes to improve and modernize the station by improving mobility and access for buses, cars, pedestrians, and bicyclists and opening the plaza slab to maximize access to daylight and air at the concourse level to create a safe, efficient, and spatially captivating station experience.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete

Environmental and Community Outcomes

Categories
Social and Economic Impacts (e.g., environmental justice, displacements)

Modernization: The Project will improve and modernize the station by opening the plaza slab beneath a new, larger canopy designed to avoid pooling of water, and to maximize access to daylight and air at the plaza and concourse levels, which improves transit rider safety. The Project includes a complete repaving and waterproofing replacement to the plaza level and repaving of the concourse level. Both of these efforts will work with the stormwater management trenches to prevent water penetration onto the tracks and platforms below.

Placemaking: The new design will emphasize visual and physical connections to create a safe, efficient, and spatially captivating station experience which will provide improved wayfinding signage, real-time arrival information, and includes new amenities such as Wi-Fi, blue light/emergency phone, etc.  The concourse level will feature new station vendor areas and public art, while the plaza level will provide spaces for community activities, greenspace, and additional displays of public art. Strengthening the east-west flow of the newly exposed concourse level between the Forsyth and Peachtree entrances provides direct sightlines to fare control, while adjacent walls can be transformed to retail frontages and murals to add activity and color to the station concourse.