FM 2100 (SH 99 to Huffman Cleveland Rd) North

PROJECT WEBSITE: https://www.txdot.gov/projects/hearings-meetings/houston/2023/fm2100-huffman-cl…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/13/2024

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The proposed improvements include widening the two-lane facility to four lanes by adding one 12-foot-wide travel lane in each direction, a 30-foot-wide raised median, a 5-foot-wide sidewalk on the east side of FM 2100, a 10-foot-wide side path on the west side of FM 2100, and open drainage ditches. 

The proposed ROW varies approximately 150 feet in width. Two new open drainage channels are also proposed. Proposed drainage channel 1 is approximately 31.5 acres and is located on the east side of FM 2100 and south of Meyer Road. Proposed drainage channel 2 is approximately 6.9 acres and is located on the east side of FM 2100 and south of proposed drainage channel 1. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete