FM 664
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/25/2020
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
FM 664 widening from IH 35E to IH 45.
TxDOT proposes improvements for Farm to Market Road (FM) 664 from Interstate Highway (IH) 35 East (E) in Red Oak to IH 45 south of Ferris in Ellis County, Texas.
The proposed FM 664 project would consist of improvements to 9.96 miles of FM 664; 1.70 miles of Interstate Highway (IH) 35 East (E); and 1.24 miles of IH 45 in Ellis County, Texas.
Improvements along FM 664 would be constructed from IH 35E in Red Oak to IH 45 south of Ferris.
The improvements to FM 664 would include widening FM 664 from two-lanes to six-lanes and the construction of a new location, 2.3-mile bypass south of the City of Ferris.
The 2.3-mile bypass would connect to a new interchange at IH 45.
Major interchanges are proposed at IH 35E at the western terminus and at IH 45 at the eastern terminus.
Ramp reconfigurations along IH 35E would convert the standard diamond interchange to an x-ramp style.
The new IH 45 interchange would be a standard diamond configuration.
The total project length is 12.90 miles.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|