Friedman Memorial Airport – Land Acquisition and Obstruction Removal (trees), Environmental Assessment

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/30/2019

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation

SECTOR
Aviation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Description:

The Federal Aviation Administration (FAA) is considering actions requested by the Friedman Memorial Airport Authority (FMAA) to correct the non-standard conditions related to identified obstructions to airspace nearest the Runway 31 End (southern end of the Airport). Penetrations in the 14 Code of Federal Regulations (CFR) Part 77 Approach Surface and Advisory Circular (AC) 150/5300-13A Departure Surface (herein after “Approach and Departure Surfaces”) consists of approximately 200 trees (primarily cottonwoods). The Friedman Airport Layout Plan (ALP) illustrates the known obstructions that are individual trees or groups of trees. Any tree that penetrates the Approach and/or Departure Surfaces, or that have the potential to penetrate these surfaces will be removed under the Proposed Action after the acquisition of the land. The Proposed Action will ultimately transfer the ownership/control of the Runway 31’s Runway Protection Zone (RPZ) to the Airport; enhance the operational safety utilization of the Runway; and, protect the Airport’s instrument approaches.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete