Geary Corridor Bus Rapid Transit Project
PROJECT WEBSITE: Geary Corridor Bus Rapid Transit Project Website
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/15/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Other Agencies with Actions or Authorizations:
California
Description:
The Geary corridor is among the most heavily-used transit corridors in San Francisco, connecting communities between the Outer Richmond and Downtown, over the entire six-mile length of the Geary Corridor. Over 50,000 daily transit riders rely on Geary bus service. San Francisco County Transportation Authority (SFCTA) and San Francisco Municipal Transportation Agency are proposing enhancements to improve the bus line's travel times, reliability, and rider comfort. The proposed Bus Rapid Transit (BRT) project would improve performance by establishing physically separated bus lanes, installing transit-optimized traffic signals, increasing bus frequencies, and building high quality stations.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|