USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Georgetown County Airport Land Acquisition and Obstruction Removal for Runway 05/23, Environmental Assessment

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/31/2017

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation

SECTOR
Aviation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Description:

An Environmental Assessment (EA) was prepared for proposed land acquisition and obstruction removal at Georgetown County Airport (GGE) subject to the National Environmental Policy Act (NEPA). The Federal Aviation Administration (FAA) is the lead federal agency for the NEPA document.  

The proposed project at the airport includes the following:
• Land Acquisition of 2 parcels to allow for clearing approach to Runway 05
• Acquisition of avigation easements from 8 parcels for clearing approach to Runway 05
• Land acquisition of 4 parcels to allow for clearing approach to • Runway 23Acquisition of avigation easements from 10 parcels too allow clearing approach to Runway 23
• Removal of obstructions within approach slopes and/or departure surface for Runway 05/23

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete