Gulf Coast Parkway (from CR386/US98 to US231)

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/04/2020

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Florida

LEAD AGENCY
Florida

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Description:

The purpose of the proposed Gulf Coast Parkway is to improve mobility by increasing the regional transportation network, increase security of the Tyndall Air Force Base (AFB), enhance economic development in Bay and Gulf Counties, and improve emergency evacuation of Gulf and Bay Counties.

The Gulf Coast Parkway would provide what is essentially a missing link in the regional transportation network and would:

  • Stimulate economies within the region
  • Enhance regional mobility and hurricane evacuation
  • Increase Tyndall Air Force Base security
  • Relieve traffic congestion

FDOT has completed the Project Development and Environment (PD&E) Study for this project. Due to the length of the project and the availability of funding, the project will be constructed in segments. Whether an interim two-lane typical section is constructed initially and widened when traffic warrants, or the ultimate four-lane typical section is constructed, will depend on whether the segment being constructed uses an existing road alignment and traffic demand justifies the full four-lane. The first segment to be advanced has right-of-way acquisition scheduled for FY2019/2020 and construction scheduled for FY 2020-2021. All remaining segments, regardless of phase, are not planned to begin until after 2040. Environmental impacts will be re-evaluated as segments advance to subsequent phases in the transportation delivery process. Additional details are available on the Gulf Coast Parkway web site at: http://gulfcoastparkway.com/ or https://nwflroads.com/projects/410981-2.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete