Hampton Harbor Bridge Poject
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/30/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
The purpose of the project is to address the state's No. 1 priority red-list bridge, the Hampton Harbor Bridge which carries NH Route 1A over Hampton Harbor Inlet in Hampton Beach, NH. The bridge is considered a vital transportation link in the region, accommodating up to 18,000 vehicles per day during peak periods, but the bridge is structurally deficient and functionally obsolete. The project also proposes to improve pedestrian and bicycle mobility. The existing bridge is one of only two historic Bascule Lift Bridges remaining in NH and, currently accommodates maritime navigational traffic. As a result, close coordination with resource agencies and project stakeholders in completing the Section 106, Section 4(f) and US Coast Guard Permit reviews will be necessary. Build Alternatives to be considered currently include bridge rehabilitation, replacement-in-kind or replacement with a fixed span bridge structure.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|