Hazel Avenue/U.S. 50 Interchange Project

PROJECT WEBSITE: https://sacdot.saccounty.net/Pages/Project-Hazel-StateRoute50.aspx

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/02/2020

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The County of Sacramento (County), in cooperation with California Department of Transportation (Caltrans) and the City of Rancho Cordova, is proposing the Hazel Avenue/U.S. Route 50 (US 50) Interchange Project (proposed project) to modify the existing interchange, and extend and grade-separate Hazel Avenue over Folsom Boulevard and the Sacramento Placerville Transportation Corridor Joint Powers Authority (SPTC-JPA) rail corridor.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete