Heber Valley Corridor EIS
PROJECT WEBSITE: Heber Valley Corridor Website
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/02/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Utah
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The Utah Department of Transportation (UDOT) is working through the Environmental Impact Statement (EIS) process to evaluate transportation solutions that would improve mobility in Heber Valley and along U.S. Route 40 (US-40) in Wasatch County, Utah. The study focuses on US-40 between State Route 32 (SR-32) and its intersection with U.S. Route 189 (US-189). The study area also extends approximately 1.5 miles both east and west of US-40, and 1.5 miles south of the US-40/US-189 intersection. On 12/11/2025 UDOT signed the Draft EIS (DEIS), the DEIS became available to the public on 1/9/2026 via the Federal Register. Comments are due by 3/9/2026, see project website for more information.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|