Highway 252/I-94
PROJECT WEBSITE: https://www.dot.state.mn.us/metro/projects/hwy252study/index.html
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/23/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
States
Department of the Interior, National Park Service
Description:
Hwy 252 and I-94 in Brooklyn Center, Brooklyn Park and north Minneapolis need improvements and repairs. Currently, people who use Hwy 252 experience a high number of crashes and heavy traffic congestion, and they feel unsafe walking, biking or rolling across the highway. In fact, three of the existing intersections along Hwy 252 have historically ranked in the top 10 in crashes statewide. These challenges impact the cohesiveness and livability of the surrounding communities and the commuters traveling on Hwy 252 on a daily basis.
The purpose of the Hwy 252/I-94 Project is to improve the safe and reliable movement of people and goods across multiple modes on and across Hwy 252 and I-94 between Hwy 610 and North 4th Street in Minneapolis.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|