Hillsboro Airport 13R-31L Runway Improvements and Runway Safety Area Improvements Environmental Assessment

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/31/2021

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation

SECTOR
Aviation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Description:

The Port of Portland (Port) is planning to modify features at Hillsboro Airport (HIO) to meet current Federal Aviation Administration (FAA) airfield design standards for Runway 13R-31L and its runway safety area (RSA). The northern portion of Runway 13R-31L and the portion of the RSA northwest of the end of Runway 13R do not fully comply with FAA design standards for longitudinal gradients. The longitudinal gradient is the grade or slope along the length of the runway and the part of the RSA that extends beyond the runway. This project will bring the grades on Runway 13R and the Runway 13R RSA and the other deviations in the Runway 13R RSA into compliance with current FAA design standards.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete