I 10 Connect
PROJECT WEBSITE: I-10 Connect Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/28/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Other Agencies with Actions or Authorizations:
Advisory Council on Historic Preservation
Description:
The I-10 Connect Project is at the convergence of US 54 and I-10 in El Paso County. The project extends from I-10 to Loop 375 (César Chávez Border Highway) and provides access to the Bridge of the Americas (BOTA) Port of Entry. Currently, only the westbound Loop 375 to westbound I-10 traffic movement has direct access between I-10 and Loop 375. The three other connections from I-10 to Loop 375 require commuters and commercial trucks to divert from the freeway and use local roadways. The existing configuration on I-110 leading to the Port of Entry experiences excessive congestion during peak periods of the day, resulting in spillbacks to US 54 and the I-10 connector ramps. This project may require the acquisition of additional right of way.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|