I-10 ExpressLanes Extension
PROJECT WEBSITE: https://www.metroexpresslanes.net/i-10-expresslanes-extension-from-i-605-to-san…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/25/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The Los Angeles County Metropolitan Transportation Authority (Metro), in cooperation with the California Department of Transportation (Caltrans) District 7 (D7) proposes to address High Occupancy Vehicle (HOV) degradation, improve mobility, provide multi-modal travel options, and address the ExpressLane gap on I-10 between I-605 and Los Angeles/San Bernardino County Line through the conversion of the existing HOV lane into an High Occupancy Toll Lane (HOT)/ExpressLane with the possible addition of a second ExpressLane or HOV lane in each direction.
This proposed project will improve safety, enhance regional connectivity, promote equitable and sustainable multi-modal travel options, encourage carpooling and transit, improve trip reliability, minimize degradation
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|