I-10 Pavement Rehabilitation Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/08/2019
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:
California
Description:
The California Department of Transportation (Caltrans) proposes to rehabilitate the existing asphalt concrete (AC) pavement on Interstate 10 (I-10) from West of the SR-177/I-10
Separation, at Post Mile (PM) R104.9, to 1.05 miles west of the Wiley’s Well Road Overcrossing (PM R134.0) in the County of Riverside. Rehabilitation activities include removal and
replacement of existing inside and outside shoulders, guardrails, rumble strips, drainage inlets, and dikes, and installation of oversized drains. The proposed project will also involve upgrades to ramp facilities for ADA compliance, installation of two temporary detour lanes in the existing median, extension of existing rock slope protection (RSP) at 44 bridge locations, and hydroseeding the median for erosion control and vegetation restoration.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|