I-11,I-515, I-215 Henderson Interchange Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/11/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
The Build Alternative includes the following major components:
- Crossover style interchange for the east-west highway directions,
- Reconnection of travel from Lake Mead Parkway to Gibson Road using braided ramps,
- Travel between I-215 and Auto Show Drive using braided ramps,
- Re-use of 22 out of the 27 existing bridges in the project area,
- Built-in capacity to add a future lane in each direction between I-215 and I-515, either as general purpose or HOV lanes,
- Auxiliary lanes on I-11 between Horizon Drive and the system interchange, and
- Arterial street improvements on Lake Mead Parkway east of the system interchange to Van Wagenen.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|