USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

I-15 EIS; Farmington to Salt Lake City

PROJECT WEBSITE: Project Website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/15/2026

3 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Utah

LEAD AGENCY
Utah

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

As part of its mission to improve quality of life through transportation, the Utah Department of Transportation (UDOT) has initiated an Environmental Impact Statement along the I‑15 corridor between Farmington and Salt Lake City. The proposed project study area extends on I-15 from the Park Lane interchange (I-15 milepost 325) in Farmington to the 400 South interchange (I-15 milepost 308) in Salt Lake City.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete